The use of property bears a social function, and all economic agents shall contribute to the common good

Section 19, Article XII of the 1987 Constitution provides: "The State shall regulate or prohibit monopolies when the public interest so requires. No combinations in restraint of trade or unfair competition shall be allowed."

The State grants electricity distribution utilities, through legislative franchises, a regulated monopoly within their respective franchise areas. Competitors are legally barred within the franchise areas of distribution utilities. Facing no competition, distribution utilities can easily dictate the price of electricity that they charge consumers. To protect the consuming public from exorbitant or unconscionable charges by distribution utilities, the State regulates the acquisition cost of electricity that distribution utilities can pass on to consumers.

As part of its regulation of this monopoly, the State requires distribution utilities to subject to competitive public bidding their purchases of electricity from power generating companies. Competitive public bidding is essential since the power cost purchased by distribution utilities is entirely passed on to consumers, along with other operating expenses of distribution utilities. Competitive public bidding is the most efficient, transparent, and effective guarantee that there will be no price gouging by distribution utilities.

Indeed, the requirement of competitive public bidding for power purchases of distribution utilities has been adopted in the United States, Europe, Latin America, India, and many developing countries.[1] This requirement is primarily aimed at ensuring a fair, reasonable, and least-cost generation charge to consumers, under a transparent power sale mechanism between the generation companies and the distribution utilities.

Section 6, Article XII of the 1987 Constitution provides: "The use of property bears a social function, and all economic agents shall contribute to the common good. Individuals and private groups, including corporations, cooperatives, and similar collective organizations, shall have the right to own, establish, and operate economic enterprises, subject to the duty of the State to promote distributive justice and to intervene when the common good so demands."

Indisputably, the use of electricity bears a vital social function. The State, in requiring competitive public bidding in the purchase of power by distribution utilities, has exercised its constitutional "duty x x x to intervene when the common good so demands."
x x x
The ERC does not have the statutory authority to postpone the date of effectivity of CSP, and thereby cannot amend the 2015 DOE Circular. As a result, the 90 PSAs submitted to the ERC after the effectivity of CSP on or after 30 June 2015 cannot serve as basis to pass on the power cost to consumers. The ERC must require CSP on all PSA applications submitted on or after 30 June 2015.

xxx
As will be herein discussed, absent the approval of and coordination with the Department of Energy (DOE), the ERC cannot suspend the effectivity of the CSP, which process was originally mandated under DOE Department Circular No. DC2015-06-0008,[4] entitled "Mandating All Distribution Utilities to Undergo Competitive Selection Process (CSP) in Securing Power Supply Agreements (PSA)" (DOE Circular). However, as will be elaborated upon below, I qualify my concurrence in that: (a) only ERC Resolution No. 01, Series of 2016 - and not the first paragraph of Section 4 of ERC Resolution No. 13, Series of 2015 - should be declared null and void; and (b) pursuant to the doctrine of operative fact, the effects of the PSAs already approved prior to the invalidity of ERC Resolution No. 01, Series of 2016, notwithstanding their CSP non-compliance, should be recognized.

[ G.R. No. 227670, May 03, 2019 ]

ALYANSA PARA SA BAGONG PILIPINAS, INC. (ABP), REPRESENTED BY EVELYN V. JALLORINA AND NOEL VILLONES, PETITIONER, VS. ENERGY REGULATORY COMMISSION, REPRESENTED BY ITS CHAIRMAN, JOSE VICENTE B. SALAZAR, DEPARTMENT OF ENERGY, REPRESENTED BY SECRETARY ALFONSO G. CUSI, MERALCO, CENTRAL LUZON PREMIERE POWER CORPORATION, ST. RAPHAEL POWER GENERATION CORPORATION, PANAY ENERGY DEVELOPMENT CORPORATION, MARIVELES POWER GENERATION CORPORATION, GLOBAL LUZON ENERGY DEVELOPMENT CORPORATION, ATIMONAN ONE ENERGY, INC., REDONDO PENINSULA ENERGY, INC., AND PHILIPPINE COMPETITION COMMISSION, RESPONDENTS.

No comments:

IN THE MATTER OF THE ALLEGATIONS CONTAINED IN THE COLUMNS OF MR. AMADO P. MACASAET PUBLISHED IN MALAYA DATED SEPTEMBER 18, 19, 20 AND 21, 2007. D E C I S I O N

  Republic of the Philippines SUPREME COURT Manila EN BANC A.M. No. 07-09-13-SC             August 8, 2008 IN THE MATTER OF THE ALLEGATIONS ...